A few of our recent contracts include:
Tongaat Quarry – Durban

Tongaat Quarry – Durban

LOAD & HAUL SERVICES – TONGAAT QUARRY, DURBAN

Client: Lafarge Mining South Africa (Pty) Ltd
Date: Jun 2019 – ongoing (3 year contract)
Volumes: 45 000 tons per month
Value: R21 627 000

Scope of works: Load and haul blast material to the primary crusher and honey hole stockpile.

Ridgeview Quarry – Durban

Ridgeview Quarry – Durban

LOAD & HAUL SERVICES – RIDGEVIEW QUARRY, DURBAN

Client: Lafarge Mining South Africa (Pty) Ltd
Date: May 2018 – ongoing (Initial 12 Month contract which has been extended to a 3 year contract)
Volumes: 90 000 tons per month
Value: R50 762 400

Scope of works: Load and haul blast material to the primary crusher and honey hole stockpile.

REHABILITATION OF AIRSTRIP – GREYTOWN, KWA-ZULU NATAL

Client: Plennegy (PTY) LTD
Date: Feb 2020 – May 2020
Volumes: 90 000 tons per month
Value: R1 700 000

Scope of works: Earth drainage, runway crack sealing and premixing on runway section.

MIDWAY CROSSING, KWAZULU NATAL

MIDWAY CROSSING, KWAZULU NATAL

CONSTRUCTION OF BULK EARTHWORKS PLATFORM FOR MIDWAY MALL - MIDWAY CROSSING, KWAZULU NATAL

Client: Siveni Investments (PTY) Ltd
Date: 19 July 2019 – March 2020
Volumes: 93 000m3
Value:
R13 313 950

Scope of works: Construction of Bulk Earthworks platform for Midway Mall

Erasmusrand Bridge – Pretoria

Erasmusrand Bridge – Pretoria

CONSTRUCTION OF NEW PEDESTRIAN BRIDGE – ERASMUSRAND, PRETORIA

Client: SANRAL
Date: Aug 2018 – Jun 2019 (10 Months)
Value: R21 573 027

Scope of works: Construction of pedestrian bridge.

Roads And Side Walks – Durban

Roads And Side Walks – Durban

CONSTRUCTION OF MINOR ACCESS ROADS AND SIDE WALKS – KWAMASHU, DURBAN

Client: Ethekwini Municipality
Date:Aug 2017 – Jan 2018 (4 months)
Value: R786 178

Scope of works: Bulk excavations, layerworks, kerbing, channelling, premix surfacing, sidewalks, and gabion installations.

Sishen Mine – Northern Cape

Sishen Mine – Northern Cape

MODULAR PLANT EXPANSION & PROJECT HANDLING FACILITY - SISHEN MINE, NORTHERN CAPE

Client: Stefanutti Stocks Mechanical
Date: Jun 2017 – Jun 2018 (12 month duration)
Value: R30 739 953

Scope of works: Bulk earthworks, including the removal of old foundations and soil improvements, excavations and various reinforced concrete structures.

Mafube Project – Mpumulanga

Mafube Project – Mpumulanga

MAFUBE COAL MINE LIFE EXTENSION PROJECT – MIDDELBURG, MPUMULANGA

Client: SMEI Projects Newco (Pty) Ltd
Date: Jan 2017 – Jul 2018 (18 months)
Value: R44 081 506

Scope of works: Bulk earthworks and civil construction of a 7.2 km coal conveyor.

FABRICATION AND ERECTION OF 12 METER HIGH FREESTANDING SQUARE LATTICE TOWER – PORT ELIZABETH, EASTERN CAPE

Client: Sentech
Date: Aug 2018 – Nov 2018 (4 Months)
Value: R739 907

Scope of works:
Supply, fabricate and erection of tower.

NOKENG TAILINGS STORAGE FACILITY – RUST DE WINTER, LIMPOPO

Client: Sepfluor Mine
Date: May 2018 – Aug 2018 (4 Months)
Value: R13 849 379

Scope of works:
Construction of Phase 1 of the tailings storage facility for Nokeng Fluorspar mine.

REPAIR OF INTERNAL CRACKS ON BULK ASH SILO – WITBANK, MATLA POWER STATION, MPUMALANGA

Client: Eskom
Date: Mar 2017 – Sep 2018 (7 months)
Value: R2 004 242

Scope of works: Repair of Bulk Ash Silo 2, internal cracks.

CONSTRUCTION OF BALANCING TANK, LOW LEVEL SCHEME PHASE 3 – NOOITGEDAAGT COEGA, PORT ELIZABETH

Client: Stefanutti Stocks Coastal
Date: Nov 2017 – Feb 2018 (4 months)
Value: R1 336 903

Scope of works: Layerworks and concrete works that formed the water retaining structure.